CONNECTING “RYAZANSKY” INDUSTRIAL PARK TO TECHNICAL COMMUNICATIONS TO BE COMPLETED BEFORE SCHEDULE

Текст новости

On October 18, the head of the region, Nikolay Lyubimov, and the CEO of the Ryazan Region Development Corporation Artem Nikitin, held an off-site meeting with the management of the contractor. It focused on accelerating the construction of engineering connections in the territory of the "Ryazansky" industrial park.

Currently, work is underway to provide power supply to the site. At the end of December, a power line will be ready for operation, through which voltage will be supplied to the 110 kWt “Razvitie” substation. The main gas supply pipeline has already been laid to the territory of the park. The work on construction and technological connection of a water chamber and a sewage pumping station is close to completion. The foundation pits for the construction of local treatment facilities are already under construction.

Excavation works are being completed for installing of the lower structure of the non-public railroad that will connect the territory of the industrial park with the branch of Moscow Railways. Now the contractor is building engineering networks and communications that lie within the construction site and outside it and installing a sewage system.